Construction Liens – Procedure and Jurisdiction

Construction Liens – Procedure and Jurisdiction

By:

Mann Lawyers

Posted November 3, 2020

Ontario’s Construction Act sets out the steps that a contractor or supplier must take in order to first “preserve” and then “perfect” a construction lien – that is, to prevent it from expiring. Preservation occurs by registering a lien with the Land Registry Office within 60 days of the date that the construction contract was completed or substantially performed (how to determine this date will be discussed in a future article). Perfection then must occur within 90 days of the last date on which preservation could have occurred. Perfecting a preserved lien requires a lien claimant to commence a court action to enforce the lien, and to file a corresponding Certificate of Action with the Land Registry Office.

Once these steps are completed, the lien will be prevented from expiring and the lien claimant will have some security for their claim. A perfected lien will expire, however, two years after the date on which the court action to enforce the lien was commenced, unless the court has ordered by that time that the action be tried, or has set the action down for trial. The expiry of a perfected lien at that point will not prevent a claimant from continuing to pursue damages against the defendant, but it will deprive the claimant of the security offered by a lien.

Jurisdiction

Section 50 of the Construction Act specifies that an action to enforce a lien must proceed in the Superior Court of Ontario. However, many claims for lien arise out of disputes involving an amount that is ordinarily within the monetary jurisdiction of the Small Claims Court, which covers claims up to $35,000.00. Unfortunately, the clear language of section 50 prevents a lien claim from being commenced in the Small Claims Court.

Amendments to the Construction Act in 2018 created a method to have lien claims transferred from the Superior Court to the Small Claims Court where the amount in dispute falls within the monetary jurisdiction of the latter. Section 58 of the Construction Act provides that, after all pleadings have been filed, any party may bring a motion to have the action transferred to the Small Claims Court.

Practical Considerations

A potential issue with moving a lien claim to the Small Claims Court is that the steps required to do so involve significant expenditure of legal fees. To have the claim heard by the Small Claims Court, a party must first pay to register their lien, then commence their action in the Superior Court, then register a Certificate of Action, and then finally bring a motion to have the action transferred – a procedure that itself involves several steps and significant expense, particularly if the motion is contested.

The overall benefit of a more efficient procedure with the Small Claims Court is likely not worth the expense involved in getting there – particularly when recognizing that the Construction Act already mandates that Superior Court lien claims are to proceed in an efficient and “summary” manner as much as possible. Accordingly, the only time it would be worth it to have a claim moved to Small Claims Court would be when all parties to the action consent to the transfer motion.

Given the complex and often strict rules involved in advancing a lien claim in the Superior Court, any potential claimant would be well advised to retain experienced counsel to do so.

This blog post was written by Brett Hodgins, a member of the Commercial Litigation team.  He can be reached at 613-369-0379 or at brett.hodgins@mannlawyers.com.

More Resources

Blog |
Business Law
By: 

Posted April 22, 2025

You have signed a commercial lease with a landlord, but the landlord will not vacate or remove its property from the leased premises. What are[...]
Blog |
Wills, Trusts and Estates
By: 

Posted April 15, 2025

When one considers drawing up a last Will, one of the most important decisions, if not the most important, is who the beneficiaries are. In[...]
Blog |
Family Law
By: 
Navigating a divorce is undoubtedly a challenging and emotional process. If you are considering divorce in Ontario, it is important to understand the process and[...]
Blog |
Environmental Law
By: 
This blog post provides a high-level overview of the federal government’s recent final State of Per- and Polyfluoroalkyl Substances (PFAS) Report (the “Report”) and accompanying[...]
Blog |
Real Estate
By: 
Ontario’s real estate market can present a rewarding opportunity for non-residents buying or selling property, but it requires careful planning and expertise. There are a[...]
Blog |
Wills, Trusts and Estates
By: 

Posted March 11, 2025

Life is unpredictable, and while it’s easy to assume that we will always be able to make our own decisions, there might come a time[...]
Brett Hodgins

Brett Hodgins

I practice primarily in corporate and commercial litigation, although I have represented clients on matters as diverse as employment issues, wrongful dismissals, estate disputes, landlord tenant matters, and real estate disputes. I have appeared on behalf of clients in the Ontario Superior Court and the Small Claims Court, the Federal Court of Canada, the Federal Court of Appeal, and before various tribunals including the Human Rights Tribunal of Ontario, the Landlord and Tenant Board, and the Parole Board of Canada. I have represented a wide variety of businesses and individuals in my practice, and I am keenly aware of the stress and costs faced by clients engaging in any kind of litigation. My guiding principle in every matter is to achieve the best possible result as efficiently and expeditiously as possible so that clients can get on with their lives. Prior to joining Mann Lawyers I completed my articles and... Read More

Read More About Brett Hodgins